PROJECT TIMELINE
The below schedule may vary depending on the actual timing of the client’s approval of the layouts and/or the confirmation of the rendered pool shell dimensions by the Master Contractor or pool builder. This latter confirmation is required to ensure that the actual finished pool walls and floor dimensions (rendered with its finish) comply with the tolerances set forth in the client approved layouts prior to fabrication activities of your movable pool floor
WEEK 01 # Purchase Order - Deposit Payment
Engineering and drafting team working our the integration drawings of your project
WEEK 4 # Drawings issuance - Second payment
Once the drawings are issued. Our project manager is meeting with you, your architect, your pool builder to validate the drawings and all technical parameters
WEEK 4 # Drawings issuance - Second payment
WEEK # 14 - Equipment ready - Third payment
Manufacturing activities completed. Floor structure ready for shipping
WEEK # 14 to 17
Equipment delivery. Shipping time depending on geographical location
WEEK # 14 to 17
WEEK # 17 to 20
Installation period. Unikpools ’s technical team travelling 48h before equipment is scheduled to arrive onsite
WEEK # 18 to 20
Floor inspection and commissioning - Installation duration depending on pool size and options
WEEK # 18 to 20